2/28/07: Release 2.6, which includes Court Calendar exchanges will be launched in production.
Next Cordele Judicial Circuit
Data Exchange Meeting: 3/22/2007 at 10 a.m. in the Crisp County Courthouse.
Last
Meeting: 2/23/07:
Cordele Judicial Circuit Minutes
Previous Meeting Minutes
Project Phases
Phase I-
Information mapping, evaluation, and project planning
•
Using JIEM tool, map information exchanges as they exist in Crisp
County (Map Complete)
•
Evaluate information exchange map, and identify crucial exchanges (Warrant/arrest
information identified)
•
Using JIEM tool, develop model for automation system to be installed in
Crisp County (Complete)
•
Select vendor to develop and install temporary Proof of Concept
platform (Metatomix selected)
Phase II- Proof
of Concept Development
•
Work with Middleware vendor selected in Phase I to develop integration
plan (ongoing throughout phase II)
•
Demonstrated ability to read database of each participating agency (successful
reads of DA, Public Defender, & Magistrate Court)
•
Demonstrate ability to write to each database of each participating
agency (successful writes to DA and
Public Defender)
•
Perform test integration with live data (Complete)
•
Install integration platform (Installed and running)
Phase III- Proof
of Concept Demonstration and Evaluation
•
Evaluate Proof of Concept Demonstration for 90 day period (Complete)
•
Identify flaws and corrections to be made for fully operational system (Complete)
•
Release RFP to qualified vendors (Complete)
•
Select vendor to install full system (Complete: Metatomix has been
chosen to build the full-time production system.)
Phase IV- System
Operation
•
Criminal Justice Agencies in Crisp County Use the integration features
daily
|